Thursday 21 May 2015

Day 23 at the new Drunken Monkey

時序走到了第23天,終於到了油漆的時候!今明兩天應該會完成大部分的油漆,接著我們的啤酒桌也會送到了!下週一則是廚房設備的到來,所有的東西一一到齊,就萬事俱全,只欠悟空了!(悟空也會趕快準備好開始做菜的!!!)
今天還有另一個意外讓人驚喜的進度就是天然瓦斯管的裝錶及拉管!因為師傅本來望著昨天的大豪雨,不顧我的三催四請要延宕今天的工程進度,不過一早他們還是出現了!所以也順利地完成了我們天然瓦斯部分的管線!
Finally, it's time to paint!  Two days of painting and then our signature picnic tables will be arriving.  Next week our kitchen equipment arrives so keep your eyes open for that as well.  Our natural gas lines just went in today as well.  We're happy the gas guys even showed up, since they said they don't work on rainy days.. even if the job is indoors.  Go figure.  Anyway they showed, so here's some pictures!

Yup, that's the right orange
這個橘色就對了



Gas line going in
瓦斯管洗洞進廚房來

Beautiful gas hookups
一隻隻瓦斯口